This is an Administrative Penalty Action (Expedited Settlement Agreement), pursuant to CAA 112(r)(7), issued to General Chemical Corporation for the Bay Point Works facility in Pittsburg, CA. The violation involves failure to review and resubmit the facilities Risk Management Plan by June 21, 2004, failure to correctly identify and submit offsite consequence analyses, and failure to update emergency contact information in the RMP. The Complaint sought $2,835 and compliance. The facility is now in compliance with the requirement.