** Drainage from undiked areas not into ponds, lagoons, or catchment basins, or no diversion systems to return spills to the facility.
** Adequatae records of drainage events are not maintained.
** Aboveground tanks not subject to periodic integrity testing, such as visual, hydrosttic, and nondestructive methods, etc.
** Records of inspections of aboveground tanks are not maintained.
** Plan has inadequate or no discussion of bulk storage tanks.
** Aboveground valves and pipelines are nto inspected regularly.
** Periodic pressdure testing of the valves and pipelines is not conducted.
PENALTY AMOUNT: $1150.00