← EPA enforcement cases

Cherry Growers, Inc.

Administrative - Formal · FY2003 · — · Final Order With Penalty · 104996

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
05-2003-0520
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

On July 13, 2002 Cherry Growers. Inc., had a release of anhydrous ammonia inside of a building. The local fire department mitigated the release with 150,000 gallons of water. The water mixed with the anhydroius ammonia to form ammonium hydroxide. The facility failed to notify the National Response Center and the State Emergency Response Commission on July 15, 2002. The facility also filed to file the written follow-up report to the SERC and the LEPC. The facility also failed to submit to the SERC, the lepc the completed TIER II form for the 1999-2001 calendar years by the March 1 deadline.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown