BIG RIVER ZINC CORP

Judicial · FY2004 · — · Final Order With Penalty · 111362

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
05-2004-0704
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

Big River Zinc Corporation (BRZ) owns a zinc smelter in Sauget, Illinois. This plant is subject to, among other things, Clean Air Act (Act) provisions for the New Source Performance Standards (NSPS) for primary zinc smelters at 40 C.F.R. Part 60, Subparts A and Q. On August 15, 2003, EPA issued a Finding of Violation (FOV) to BRZ, alleging violations of the applicable NSPS regulations. More specifically, the FOV stated that BRZ had replaced the Sauget facility's two zinc roasters, affected facilities under the NSPS regulations, without providing notification to the Administrator and conducting performance tests. The FOV also alleged that BRZ was violating Subpart Q sulfur dioxide emission limits in 40 C.F.R. 60.173(a). The source ceased its zinc roasting operations in early 2006, alleging financial hardship caused by high raw material prices. Under the CD, BRZ must pay a civil penalty of $250,000, an amount based upon its poor financial condition as well as its agreement to commit to a more stringent level of control than is currently required by the primary zinc NSPS. The CD also requires BRZ to: 1) Pay stipulated penalties; 2) Apply to the Illinois EPA to incorporate Decree requirements into a federally enforceable construction permit or State Implementation Plan submission, as well as into BRZ's Title V operating permit; 3) Comply with all applicable laws in the event that BRZ decides to use its roasters for operation other than zinc roasting; and 4) Submit rep

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown