04-2008-5771
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
—
Self-disclosure
N

Defendants (3)

Summary

9/12/2008 - ADMINISTRATIVE ORDER ISSUED. ORDER STATES: COMMENCING ON OR ABOUT NOVEMBER 17, 2005, TO PRESENT, RESPONDENTS AND/OR THOSE ACTING ON BEHALF OFTHE RESPONDENTS, DISHARGED DREDGED AND/OR FILL MATERIAL INTO JURISDICTIONAL WATERS ON THE SITE USING EARTH MOVING MACHINERY, DURING UNAUTHORIZED ACTIVITIES ASSOCIATED WITH THE MECHANICAL LAND CLEARING AND FILLING OF STREAMS ASSOCIATED WITH COMMERCIAL DEVELOPMENT. RESPONDENTS' UNAUTHORIZED ACTIVITIES IMPACTED 4,950 LINEAR FEET (INCLUDING 3,650 LINEAR FEET OF PERMANENT AND TEMPORARY IMPACTS, RESPECTIVELY) OF UNNAMED TRIBUTARIES TO MCCOYS FORK, WHICH IS TRIBUTARY TO MUD LICK CREEK, WHICH IS TRIBUTARY TO BIG BONE CREEK, WHICH FLOWS INTO THE OHIO RIVER, A NAVIGABLE WATER OF UNITED STATES. AT NOT TIME DURING THE DREDGED AND/OR FILL MATERIAL AT THE DISCHARGE AREA ON OR AROUND NOVEMBER 17, 2005, TO PRESENT, DID THE RESPONDENTS POSSESS A PERMIT UNDER SECTION 404 OF THE CWA, AUTHORIZING THE ACTIVITIES PERFORMED BY RESPONDENTS.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown