← EPA enforcement cases

JDG INVESTMENTS, INC. - WHITE OAK LANDING PHASE III

Administrative - Formal · FY2009 · — · Unilateral Administrative Order Without Adjudication · 1400018640

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
04-2009-4760
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
—
Self-disclosure
N

Defendants (2)

Summary

11/28/2008 - ADMINISTRATIVE ORDER ISSUED. ORDER STATES: DURING THE CSWEI, EPA INSPECTORS OBSERBED THE FOLLOWING: A. THE PLAN WAS NOT IMPLEMENTED AS APPROVED, AS REQUIRED BY PART I.A.2 OF THE PERMIT. THE LEVEL SPREADER #3-2 DESCRIBED IN THE PLAN WAS NOT INSTALLED AT THE SEDIMENT TRAP #4 OUTFALL. THE CHECK DAMS IN THE DRAINAGE DITCHES WERE NOT INSTALLED PER THE DESIGN AND SPECIFICATIONS IN THE PLAN. B. INSPECTION REPORTS WERE MISSING FOR THE FOLLOWING DATES: 02/1/08, 03/7/08, 3/12/08, 4/25/08, 4/27/08, 4/28/08, 7/4/08, 7/5/08, 07/6/08, 07/19/08, 07/31/08, 08/20/08, 08/27/08, 08/30/08, AND 06/06/08; AND NO RAIN GAUGE WAS OBSERVED, AS REQUIRED BY PART I.B.1 OF THE PERMIT. C. INSPECTION REPORTS DID NOT INCLUDE AN EXPLANATION OF CORRECTIVE ACTIONS TAKEN TO ADDRESS SEDIMENT DISCHARGES OBSERVED ENTERING THE UNNAMED TRIBUTARY OF WHITE OAK FROM SEDIMENT TRAP #4 OFF STREET F, MEASURES TAKEN TO CONTROL FUTURE RELEASES, AND MEASURES TAKEN TO CLEAN UP SEDIMENT BEYOND THE DISTURBED LIMITS, AS REQUIRED BY PART I.B.2 AND PART I.B.3 OF THE PERMIT. D. STORM WATER CONTROLS WERE NOT BEING OPERATED AND MAINTAINED AT OPTIMUM EFFICIENCY, AS REQUIRED BY PART I.C.2 AND PART II.C.1 OF THE PERMIT. SILT FENCING ON THE SOUTHEASTERN PORTIONS OF THE DEVELOPMENT OFF STREETS D AND E NEEDED MAINTENANCE. SEDIMENT TRAP #4 OFF STREET F HAD DOUBLE-ROW SILT FENCING BELOW IT THAT NEEDED TO BE REPLACED. SILT FENCING ON THE SOUTHWESTERN PORTION OF THE DEVELOPMENT OFF STREET G NEEDED MAINTENANCE. A STORM

Source

Authoritative
EPA ECHO
Machine