5/29/09 - CONSENT AGMT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $1,773, DUE WITHIN 30 DAYS.
VIOLATIONS:
ON OR ABOUT DEC 10, 2008, AN INSPECTION WAS CONDUCTED AT RESPONDENT'S FACILITY.
AT THE TIME OF THE INSPECTION, 5 PCB-CONTAMINATED TRANSFORMERS WERE STORED IN THE PCB STORAGE AREA. NON OF THE PCB-CONTAMINATED TRANSFORMERS WERE MARKED WITH THE DATE THE PCB WASTE WAS REMOVED FROM SERVICE - IN VIOLATION OF 40 CFR 761.65(c)(8).
AT THE TIME OF THE INSPECTION, 5 PCB-CONTAMINATED TRANSFORMERS WERE STORED IN THE PCB STORAGE AREA. RESPONDENT HAD NO RECORDS DOCUMENTING THAT THESE PCB-CONTAMINATED TRANSFORMERS HAD BEEN CHECKED FOR LEAKS AT LEAST ONCE EVERY 30 DAYS - IN VIOLATION OF 40 CFR 761.65(c)(5) AND 40 CFR 761.180(a)(1)(iii).