Columbia Colstor, Inc.

Administrative - Formal · FY2009 · — · Final Order With Penalty · 1800023290

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
10-2009-0200
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

An RMP inspection was conducted on April 24, 2008 at the Columbia Colstor-Woodland Processing facility. Columbia Colstor failed to comply with 40 CFR Part 68 for process safety information and equipment, electrical classification, relief system design and design basis, ventilation system design, mechanical Integrity and hazard assessment.