← EPA enforcement cases

AltChem Environmental, Inc. (SB) et al.

Administrative - Formal · FY2009 · — · Final Order With Penalty · 1800026134

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
02-2009-1229
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (2)

Summary

Case is regarding Asbestos removal issues at former Owens Corning manufacturing plant. Respondents are the removal contractor and the facility owner. Complaint includes counts of violations against the Asbestos NESHAP regulations. Case settled by CAFO with Altchem.