PG&E Gateway (aka Mirant Delta) Judicial Action

Judicial · FY2009 · — · Final Order With Penalty · 1800027292

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
09-2009-0508
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

This is an EPA Consent Decree with Pacific Gas and Electric (PG&E Gateway)(aka Mirant Delta) for Clean Air Act Section 165 & 110 violations including construction without a valid PSD permit. Payment of a Civil Penalty, injunctive relief (including reducing substantial amounts of pollution), and obtaining the proper permit(s); as well as installing additional Nitrogen Oxide (NOx) controls by way of a special mitigation project constitute the beneficial environmental results.