← EPA enforcement cases

CSX Transportation, Inc.

Administrative - Formal · FY2010 · — · Final Order With Specified Cost Recovery · 1800074012

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
02-2010-2003
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

This is an Administrative Settlement Agreement under Section 122(h) of CERCLA that provides for payment, plus interest, representing a 100% recovery of EPA’s unreimbursed past costs associated with the Canastota/Oneida Train Derailment Site in Oneida, New York. The Respondent owned and operated the rail line where the derailment occurred in March of 2007. The derailment caused the release of inter alia, liquefied petroleum gas, toluene, and ferric chloride and the Respondent conducted a cleanup. EPA incurred costs in overseeing the Respondent's response.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown