Violation: The Respondent's tank battery facility was a point source which discharged a pollutant to a waters of US. The EPA inspected the Respondent's injection well on December 22, 2009, and observed where brine had been discharged from the facility to Cimarron River.
Relief: An Administrative Order is being issued to the Respondent requiring the following: 1) cease all discharges of pollutants from the facility; 2) remove all the brine from the flow path; 3) remove all the brine from the impacted water body; 4) submit written certification.