← EPA enforcement cases

ESTES EXPRESS LINES

Administrative - Formal · FY2010 · — · Final Order With Penalty · 1800098191

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
04-2010-7003
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

5/6/10 - SPCC SETTLEMENT AGREEMENT, ASSESSING A PENALTY OF $1,400. ALLEGED VIOLATIONS: 1. FAILURE TO PREPARE A WRITTEN SPCC PLAN FOR THE FACILITY BY 40 CFR 112.3(a) IN ACCORDANCE WITH THE GUIDELINES FOR PLAN PREPARATION AT 40 CFR 112.7. 2. FAILURE TO IMPLEMENT AN SPCC PLAN AS REQUIRED BY 40 CFR 112.3(a) IN ACCORDANCE WITH THE GUIDELINES FOR PLAN IMPLEMENTATION AT 40 CFR 112.7 AND/OR 112.8: A. SECONDARY CONTAINMENT AND/OR UNDIKED AREA DRAINAGE CONTROLS ARE NOT PROVIDED IN TANKER TRUCK UNLOADING AREAS AS REQUIRED BY 40 CFR 112.7(c) AND/OR 112.8(b)(3); B. RECORDS OF DIKE DRAINAGE EVENTS ARE NOT MAINTAINED AS REQUIRED BY 40 CFR 112.8(c)(3); C. RECORDS OF TANK INSPECTIONS OF TESTS ARE NOT MAINTAINED AS REQUIRED BY 40 CFR 112.8(c)(6); D. BULK STORAGE CONTAINER NOT EQUIPPED WITH A LIQUID LEVEL SENSING DEVICE AS REQUIRED BY 40 CFR 112.8(c)(8).

Source

Authoritative
EPA ECHO
Machine