6/9/10 - CONSENT AGMT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $20,250, PLUS INTEREST, DUE IN 12 MONTHLY INSTALLMENTS. EACH PAYMENT OF $1,696.65 DUE ON EACH OF THE FOLLOWING DATES:
JULY 1, 2010;
AUG 1, 2010;
SEPT 1, 2010;
OCT 1, 2010;
NOV 1, 2010;
DEC 1, 2010;
JAN 1, 2011;
FEB 1, 2011;
MAR 1, 2011;
APR 1, 2011;
MAY 1, 2011;
JUN 1, 2011.
RESPONDENT FAILED TO SUBMIT A COMPLETED EMERGENCY AND HAZARDOUS CHEMICAL INVENTORY FORM FOR CHLORINE TO THE SERC, THE LEPC, AND THE FIRE DEPT WITH JURISDICTION OVER THE FACILITY FOR CALENDAR YEARS 2008 AND 2007 TO THE LEPC AND FIRE DEPT FOR CALENDAR YEAR 2006 BY MARCH 1 OF THE FOLLOWING YEAR.