6/17/10 - CONSENT AGMT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $3,187, PLUS INTEREST, TO BE PAID IN 4 INSTALLMENT PAYMENTS. THE FIRST PAYMENT IS DUE WITHIN 30 DAYS AND SUBSEQUENT PAYMSN WILL BE DUE EVERY 3 MONTHS THEREAFTER.
SPECIFIC ALLEGATIONS:
RESPONDENT IS A SUBCONSTRACTOR THAT WAS PREVIOUSLY HIRED BY VARLEY CONSTRUCTION, A GENERAL CONTRACTOR, TO DEMOLISH A FACILITY THAT WAS PREVIOUSLY A TACO BELL, LOCATED AT 302 MALL BOULEVARD, IN SAVANNAH, GA.
BETWEEN JULY 10, 2009, AND SEPT 18, 2009, RESPONDENT DEMOLISHED THE FACILITY.
RESPONDENT VIOATED CAA SEC 112 AND 40 CFR 61.145(b) BY FAILING TO PROVIDE WRITTEN NOTICE OF INTENTION TO DEMOLISH THE FACILITY PRIOR TO THE INITIATION OF DEMOLITION ACTIVITIES.