← EPA enforcement cases

Lone Mountain Contracting, Inc (NMU001668)

Administrative - Formal · FY2010 · — · Final Order With Penalty · 1800119195

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
06-2010-1907
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

A stormwater compliance inspection was conducted July 13, 2010, by the New Mexico Environment Department, at the construction site of Alexander Gusdorf Eco-Park in the Town of Taos, NM, to determine compliance with the Stormwater Construction General Permit. It was determined that Lone Mountain Contracting, Inc, had failed to submit a Notice of Intent for permit coverage and did not have a Stormwater Pollution Prevention Plan. An Expedited Settlement Offer was extended to quickly settle the issues and collect a penalty for the violations.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown