Town of Taos (NMU001669)

Administrative - Formal · FY2010 · — · Withdrawn by Region/State · 1800119203

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
06-2010-1906
Type
Administrative - Formal
Lead
EPA
Outcome
Withdrawn by Region/State
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

stormwater compliance inspection was conducted July 13, 2010, by the New Mexico Environment Department, at the construction site of Alexander Gusdorf Eco-Park in the Town of Taos, NM, to determine compliance with the Stormwater Construction General Permit. It was determined that the Town of Taos had failed to submit a Notice of Intent for permit coverage and did not have a Stormwater Pollution Prevention Plan. An Expedited Settlement Offer was extended to quickly settle the issues and collect a penalty for the violations.