This is an administrative settlement for DOJ approval that resolves a past cost demand made to the Respondent. The Respondent sent computer chip racks to the Site operator to be cleaned. The cleaning process involved the use of solvents, which were disposed of at the Site and migrated to the groundwater. The Respondent was notified of its status as a PRP in June of 2000, and has undertaken removal work and the RI/FS at the Site.
By letter dated August 17, 2004, EPA sent Respondent a demand for unreimbursed past costs from June 1, 2000 through April 30, 2004 for the Shenandoah Road Groundwater Contamination Site. The costs were primarily removal costs incurred by EPA prior to entering into the removal order with the Respondent.