PEPPER'S STEEL AND ALLOYS INC.

Judicial · FY1983 · — · Final Order With Specified Cost Recovery · 20179

—
Penalty
$1.16M
Cost recovery
—
Compliance action

Case

Case Number
04-1983-0012
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
DOJ Docket
90-11-2-62A
Multimedia
N
Self-disclosure
N

Defendants (15)

Summary

COURT DOCKET NUMBERS: 1983 CD - 83-1717-CIV-SPELLMAN; 1997 CD- 85-0571-CV-EDB-DAVIS. PEPPERS STEEL AND ALLOYS IS A SCRAP METAL FACILITY THAT HAS BEEN IN OPERATION SINCE THE EARLY 70'S. SOME METAL RE- COVERED CONSISTED OF ELECTRICAL TRANSFORMERS OBTAINED FROM FLA. POWER & LIGHT. PEPPERS DRAINED THE TRANSFORMER OIL, SOME OF WHICH CONTAINED PCB'S, ON ITS PROPERTY. THE SITE IS SITUATED OVER MARSHLAND AND IS UNDERLAIN BY THE BISCAYNE AQUIFER, WHICH SUPPLIES MUCH OF THE DRINKING WATER TO SOUTH- EASTERN FLA. IN JANURARY 1983 EPA WAS CONTACTED BY DADE CO- UNTY OFFICIALS CONCERNING REPORTS BY FORMER EMPLOYEES THAT LARGE QUANTITIES OF TRANSFORMER OIL CONTAMINATED WITH PCB'S HAD BEEN DISCHARGED DIRECTLY INTO THE SOIL AT THE PEPPER'S STEEL & ALLOYS, INC. FACILITY IN MEDLEY, FL. THE COUNTY ALSO REPORTED THAT ANALYSES OF SAMPLES FROM THE SITE SHOWED HIGH PCB CONCENTRATIONS IN WHAT APPEARED TO BE A FLOATING OIL LAY ER ON TOP OF THE BISCAYNE ACQUIFER. IN JUNE 1983, EPA BEGAN IMMEDIATE REMOVAL ACTION AT THE SITE. THE ACTION INCLUDED EX TENSIVE SAMPLING TO RELOCATE THE OIL LAYER AND REMOVAL OF 1200 GALLONS OF PCB CONTAMINATED LIQUIDS. COST INCURRED TO DATE AMOUNT TO AT LEAST $388,883,79. SITE IS ON THE NPL. RECOMMENDED ACTION: THIS REFERRAL REQUESTS THAT CIVIL AC- TION BE INITIATED TO RECOVER THE COST OF THE IMMEDIATE REMO- VAL ACTION UNDERTAKEN AT THE SITE.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown