← EPA enforcement cases

SPEEDRACK PRODUCTS GROUP, LTD., INC.

Judicial · FY1994 · — · Final Order With Penalty · 21115

$192K
Penalty
—
Cost recovery
$64K
Compliance action

Case

Case Number
04-1994-0420
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
DOJ Docket
90-5-2-1-1962
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

SPEEDRACK VIOLATED THE PSD REGULATIONS BY FAILING TO OBTAIN A PSD PRE-CONSTRUCTION PERMIT PRIOR TO CONSTRUCTING A FACILITY WITH THE POTENTIAL TO EMIT IN EXCESS OF 250 TPY OF VOCS. SPEEDRACK ALSO VIOLATED THE NSPS BY CAUSING THE DISCHARGE INTO THE ATMOSPHERE OF VOCS FROM ITS METAL FURNITURE SURFACE COATING OPERATION IN EXCESS OF .90 KILOGRAM PER LITER OF COATING SOLIDS APPLIED. THE MATTER WAS DIRECTLY REFERRED TO DOJ AT THE END OF AUGUST AND RECOMMENDS A TOTAL PENALTY IN THE AMOUNT OF $1,185,701 AS WELL AS INJUNCTIVE RELIEF TO BRING THE FACILITY INTO COMPLIANCE WITH ALL APPLICABLE PSD AND NSPS REQUIREMENTS.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown