← EPA enforcement cases

JONES TIRE AND BATTERY

Judicial · FY1998 · — · Final Order With Specified Cost Recovery · 22477

—
Penalty
$600K
Cost recovery
—
Compliance action

Case

Case Number
04-1998-0107
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
DOJ Docket
90-11-2-986/1
Multimedia
N
Self-disclosure
N

Defendants (50)

Summary

SITE WAS A BATTERY-CRACKING FACILITY IN BIRMINGHAM. EPA CONDUCTED REMOVAL AND OVERSIGHT AT SITE, INCURRING COSTS OF $1.38 MILLION. MARCH 16, 1998, EPA REFERRED MATTER TO DOJ FOR FILING OF A CIVIL ACTION UNDER CERCLA SECTION 107 TO RECOVER COSTS. DEFENDANTS ARE GENERATORS, NUMBERING APPROXIMATELY 50. CIVIL ACTION FOR COST RECOVERY. LARGE ORPHAN SHARE WILL BE A CONSIDERATION IF SETTLEMENT IS NEGOTIATED.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown