The December 16, 2010 Amended AO requires system to comply with the Combined Radium MCL of 5 pCi/L, submit a letter stating its intention to comply with Amended AO, followed by a detailed plan for bringing system into compliance including milestones with dates for planning engineering/designing, obtaining funding, construction/equipment installation, and projected completion date, and, to the extent grant funding is part of the plan, a contingency funding option in case grant funds are not available. It also requires system to continue to sample quarterly for combined radium and provide public notice each quarter as long as the violations persists.
A second Amended AO was issued on December 22, 2011 to allow system time to obtain needed funding for a connection to the Village of Lewiston public water system to comply with the Combined Radium MCL of 5 pCi/L. Bryant complied with the second Amended AO on 6/17/2013.