← EPA enforcement cases

DURASOL CORP

Administrative - Formal · FY2011 · — · Final Order With Penalty · 2600016774

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
01-2011-2033
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

On August 22, 2011, Region 1 entered into an expedited settlement agreement with Durasol Corporation (Durasol) of Amesbury, Massachusetts addressing violations of the Oil Pollution Prevention regulations at 40 C.F.R. Part 112, promulgated under Section 311(j) of the Clean Water Act. An EPA SPCC inspection at Durasol revealed that the facility did not have an adequate SPCC plan. Pursuant to the agreement, Durasol paid a penalty of $8,000.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown