← EPA enforcement cases

Owego Super Mart (SB) et al.

Administrative - Formal · FY2011 · — · Final Order With Penalty · 2600018449

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
02-2011-7948
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (2)

Summary

Facility failed to maintain CP system continuously, did not have annual line tightness test or perform monthly monitoring on the pipes and did not have adequate LLD system for the underground pipes. FC issued.