← EPA enforcement cases

BRENDA MASSEY IMPOUNDMENT

Administrative - Formal · FY2011 · — · Unilateral Administrative Order Without Adjudication · 2600053236

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
04-2011-5780
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

9/14/11 - ADMINISTRATIVE COMPLIANCE ORDER ISSUED. THE ACO PERTAINS TO THE DEPOSITION OF DREDGED AND/OR FILL MATERIAL INTO JURISDICTIONAL WETLANDS AND WATERS OF THE U.S. IMPACTING APPROX 9,464 LINEAR FEET OF UNNAMED TRIBUTARIES TO PREE CREEK AND 1.18 ACRES OF ASSOCIATED ABUTTING WETLANDS. THE DEPOSITION OF DREDGED AND/OR FILL MATERIAL OCCURRED DURING THE CONSTRUCTION OF A 17-ACRE LAKE. ON OR ABOUT MAY 2010, THE ARMY COE WAS NOTIFIED THAT MASSEY DISCHARGED DREDGED AND/OR FILL MATERIAL INTO JURISIDICTIONAL WETLANDS AND WATERS INTO THE DISCHARGE AREA ON THE SITE USING EARTH MOVING MACHINERY, DURING UNAUTHORIZED ACTIVITIES ASSOCIATED WITH THE CONSTRUCTION OF A DAM TO CREATE A 17-ACRE LAKE. AT NO TIME DURING THE DISCHARGE OF DREDGED AND/OR FILL MATERIAL AT THE DISCHARGE AREA FROM MAY 2010 TO PRESENT DID MASSEY POSSESS A PERMIT ISSUED PURSUANT TO CWA 404. ORDER REQUIRES: A. IMMEDIATELY CEASE PARTICIPATING IN, CAUSING, OR ALLOWING ANY ADDITIONAL UNAUTHORIZED DISCHARGES OF ANY DREDGED AND/OR FILL MATERIAL. B. WITHIN 48 HOURS, MASSEY AND/OR HER AUTHORIZED REP SHALL NOTIFY EPA WHETHER OR NOT MASSEY INTENDS TO COMPLY WITH THIS ACO. C. WITHIN 30 DAYS, MASSEY AND/OR HER AUTHORIZED REP SHALL PROVIDE A RESTORATION PLAN TO EPA FOR REVIEW AND APPROVAL. D. IF EPA PROVIDE COMMENTS ON THE RESTORATION PLAN, MASSEY AND/OR HER AUTHORIZED REP SHALL ADDRESS ALL THE COMMENTS AND SUBMIT TO EPA A REVISED RESTORATION PLAN WITHIN 30 DAYS. E. MASSEY SHALL BEGIN IMPLEMENTATION O

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown