The December 22, 2011 second Amended AO requires system to comply with the Combined Radium MCL of 5 pCi/L as soon as possible and no later than November 30, 2012; Submit to U.S. EPA and Illinois EPA a letter stating RespondentÂs intention to comply within 10 days from receipt of this Order; Complete the following actions to bring the System into compliance with the Combined Radium MCL by completing a connection to the Village of Lewiston public water system: Advertise Bids by 2/10/12, Open Bids by 3/9/12,Loan Closing/Begin Construction by 5/18/12, and Complete Construction by November 30, 2012. The Amended AO also requires system to continue to follow current operation and maintenance procedures for the treatment process at the Village of Bryant public water system treatment plant as documented in Appendix 1 of this Amended Order, including immediately investigating increases in daily water usage, and promptly locating and fixing leaks until the Village of Bryant completes the connection to the Village of Lewiston public water system and discontinues use of its own well.
It also requires system to continue to submit to U.S. EPA and Illinois EPA in writing, a progress report on the status of achieving each identified milestone by March 31, 2012, and by the end of each subsequent calendar quarter: sample quarterly for combined radium and provide public notice each quarter as long as the violations persists.
Our records show that Bryant met the requirements of the 2