← EPA enforcement cases

NELCON INC

Administrative - Formal · FY2014 · — · Final Order No Penalty · 3400190545

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
08-2014-0004
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

Respondent consents and agrees to undertake additional stabilization efforts at the Willow Creek crossing and the portion of the Two Medicine crossing that are consistent with the Criteria for Stabilization section of the National Pollutant Discharge Elimination System General Permit for Discharges from Construction Activities.