BALLARD OIL COMPANY INC

Administrative - Formal · FY2014 · — · Final Order With Penalty · 3400264609

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
10-2014-0157
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

On September 8, 2014, Region 10 filed a Consent Agreement and Final Order resolving violations of Section 311(j) of the Clean Water Act, 33 U.S.C. §1321(j) and accompanying Spill Prevention, Control and Countermeasures (SPCC) and Facility Response Plan (FRP) regulations, 40 C.F.R. Part 112 by Ballard Oil Company Inc.. The violations were observed during an August 2012 inspection of the company’s oil storage and distribution facility in Seattle, Washington, and included failure to prepare and implement adequate FRP/SPCC Plans for the facility. The company agreed to pay a penalty of $34,100.