← EPA enforcement cases

BRACKMANN CONSTRUCTION, INC

Administrative - Formal · FY2014 · — · Final Order With Penalty · 3400290394

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
07-2014-0278
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

ON SEPTEMBER 22, 2014, EPA REGION 7 REACHED AGREEMENT WITH BRACKMANN CONSTRUCTION, INC OF BELTON, MISSOURI, IN SETTLEMENT TO RESOLVE VIOLATIONS OF SECTION 7 OF TSCA. THE VIOLATIONS WERE DOCUMENTED DURING S SITE INSPECTION ON DECEMBER 19, 2013. THE PROPERTY IN KANSAS CITY, MISSOURI MEETS THE DEFINITION OF TARGET HOUSING AND MESA ENTERPRISES, LLC WAS RESPONSIBLE FOR COMPLYING WITH RRP RULES FOUND IN 40 CFR PART 745, SUBPART E. BRACKMANN CONSTRUCTION, INC HAS REPORTED IT IS COMPLIANT WITH THE RULES. THIS CONSENT AGREEMENT AND FINAL ORDER SIMULTANEOUSLY COMMENCES AND CONCLUDES THIS ACTION AND REQUIRES BRACKMANN CONSTRUCTION, INC TO PAY A $500 PENALTY.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown