← EPA enforcement cases

MGST, INCORPORATED

Administrative - Formal · FY1995 · — · Unilateral Administrative Order Without Adjudication · 35995

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
06-1995-0121
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

1. SECTION 1423(C) OF THE SAFE DRINKING WATER ACT ( SDWA ), 42 U.S.C. SEC. 300H-2. 2. MGST, INCORPORATED ROUTE 9, BOX 10 PONCA CITY, OKLAHOMA 74601 3. RESPONDENT WAS INVIOLATION OF SECTION 1421 AND 1422 OF SDWA BY FAILING TO PLUG A WELL WITHIN ONE YEAR AFTER IN- JECTION WAS TERMINATED. 4. RELIEF SOUGHT PURSUANT TO SECTION 1423(C)(4)(B) OF SDWA, RESPONDENT IS ORDER TO PLUG THE WELL ACCORDING TO REGULA- TIONS WITHIN 15 DAYS AFTER EFFECTIVE DATE OF THIS ORDER OR PAY A PENALTY NOT TO EXCEED $125,000.00 IF THE WORK IS NOT COMPLETED ON OR BEFORE THE DATE REQUIRED IN THE OR- DER.

Source

Authoritative
EPA ECHO