Hess Corp.- Tioga Gas Plant

Administrative - Formal · FY2021 · — · Final Order With Penalty · 3602490214

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
08-2021-0068
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

October 7/2015 EPA conducted an SPCC inspection and documented SPCC Plan deficiencies, numerous technical deficiencies, including lack of secondary containment, and failure to submit an FRP for the facility.