← EPA enforcement cases

UNDERGROUND EXCAVATING, INC

Administrative - Formal · FY2022 · — · Final Order With Penalty · 3603333810

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
04-2022-0003
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

7/25/2022 - EXPEDITED SETTLEMENT AGREEMENT ISSUED ASSESSING A PENALTY OF $7,393. PENALTY DUE WITHIN 15 DAYS. ALLEGED VIOLATIONS: BASED ON INFORMATION SENT VIA ELECTRONIC MAIL TO THE EPA BY THE RESPONDENT, THE EPA ALLEGES THAT RESPONDENT VIOLATED SECTION 112 OF THE CAA, 42 U.S.C. ? 7412, AND 40 C.F.R. PART 61, SUBPART M. SPECIFICALLY, THE EPA ALLEGES THE RESPONDENT FAILED TO CONDUCT A THOROUGH INSPECTION FOR ASBESTOS-CONTAINING MATERIALS PRIOR TO BEGINNING DEMOLITION ACTIVITY, AS REQUIRED BY 40 C.F.R. ? 61.145(A), AT A COMMERCIAL BUILDING LOCATED AT OR NEAR 5753 EAST MAIN STREET IN PATTERSON, GEORGIA 31557 (THE FACILITY). THE EPA ALSO ALLEGES THE RESPONDENT FAILED TO PROVIDE WRITTEN NOTICE TO THE GEORGIA ENVIRONMENTAL PROTECTION DIVISION (EPD) 10 WORKING DAYS PRIOR TO BEGINNING THE DEMOLITION ACTIVITY, AS REQUIRED BY 40 C.F.R. ? 61.145(B). NO NOTICE WAS PROVIDED TO THE EPD. DEMOLITION COMMENCED AT THE FACILITY ON OR AROUND DECEMBER 29, 2021.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown