Rocky Reach Hydroelectric Project

Administrative - Formal · FY2023 · — · Final Order With Penalty · 3603590491

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
10-2023-0082
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

On August 10, 2023, Region 10 filed an expedited settlement agreement resolving violations of the Clean Water Act by Public Utility District No. 1 of Chelan County located in Wenatchee, WA. Respondent operates a hydroelectric dam with several operating systems containing oil in the powerhouse at their facility on the Columbia River in Central Washington. An EPA spill prevention, control and countermeasure (SPCC) inspection on November 29, 2022 determined the respondent's SPCC Plan had multiple deficiencies including failure to discuss alternative environmental protection to SPCC requirements and providing an adequate description for equipment failure that could result in discharge. The facility's oil tanks have a storage capacity of approximately 314,077 gallons. PUD No. 1 of Chelan County agreed to make amendments to the SPCC Plan for the facility's oil storage, transportation, and use and pay a penalty of $1,188 for the SPCC regulatory violations.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown