# DRILLMASTER INTERNATIONAL, A TEXAS CORPORATION
> **Administrative - Formal** · FY1998 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `38107`
- **Case Number:** 06-1998-0413
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** $4K
- **Multimedia (multi-env):** N
## Defendants
- DRILLMASTER INTERNATIONAL (complaint) (settlement)
## Summary

1. SECTION 309(A) OF THE CLEAN WATER ACT ( CWA ), 33 U.S.C.     SECTION 1319(A).                                          2. DRILLMASTER INTERNATIONAL, A TEXAS CORPORATION               1112 COMMERCIAL BOULEVARD, NORTH                             ARLINGTON, TARRANT COUNTY, TEXAS 76001                    3. RESPONDENT WAS IN VIOLATION OF SECTION 301 OF THE CWA BY     CONDUCTING THE RELEVANT ACTIVITIES AND OPERATING THE FA-     CILITY FROM OCT. 1, 1992 WITHOUT NPDES PERMIT COVERAGE.   4. RELIEF SOUGHT PURSUANT TO SECTION 309(A) OF THE CWA, EPA     ISSUED AN ADMINISTRATIVE ORDER (AO) TO THE RESPONDENT.       THE AO REQUIRES THE RESPONDENT TO, WITHIN 30 DAYS: A) AP-    PLY FOR AND OBTAIN AN NPDES PERMIT, B) TAKE WHATEVER         CORRECTIVE ACTION IS NECESSARY TO CORRECT THE DEFICIEN-      CIES AND ELIMINATE AND PREVENT RECURRENCE, C) SUBMIT A       WRITTEN REPORT DETAILING THE SPECIFIC ACTIONS TAKEN TO       CORRECT THE VIOLATIONS, WHY THEY WILL PREVENT RECURRENCE,    AND A COPY OF THE SWPPP, D, IF NOT POSSIBLE TO CORRECT       WITHIN 30 DAYS, SUBMIT A PLAN TO DO SO IN THE SHORTEST       TIME POSSIBLE.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · MORVS · CC0 1.0*