Summary

1. SECTIONS 308(A) AND 309(A) OF THE CLEAN WATER ACT ( CWA ) 33 U.S.C. SECTIONS 1318(A) AND 1319(A). 2. BRIDLEWOOD LTD., A TEXAS LIMITED PARTNERSHIP FACILITY: BRIDLEWOOD FARMS CROSS TIMBERS ROAD (FM 1171) AT HUNWICK LANE FLOWER MOUND, DENTON COUNTY, TEXAS 75028 3. RESPONDENT WAS IN VIOLATION OF SECTION 301 OF THE CWA BY: 1) THE STORM WATER POLLUTION PREVENTION PLAN (SWPPP) DID NOT IDENTIFY AND ENSURE THE IMPLEMENTATION OF APPROPRIATE POLLUTION PREVENTION MEASURES FOR THE NON-STORM WATER COMPONENTS OF THE DISCHARGE. 4. RELIEF SOUGHT PURSUANT TO SECTION 309(A) OF THE CWA, EPA ISSUED THE RESPONDENT AN ADMINISTRATIVE ORDER (AO) THAT REQUIRED THE RESPONDENT TO: A) WITHIN 30 DAYS, TAKE WHAT- EVER CORRECTIVE ACTION IS NECESSARY TO CORRECT THE DE- FICIENCIES, ELIMINATE AND PREVENT RECURRENCE OF THE VIO- LATIONS CITED, AND TO COME INTO COMPLIANCE; B) WITHIN 30 DAYS, SUBMIT A WRITTEN REPORT DETAILING THE SPECIFIC AC- TIONS TAKEN AND EXPLAIN HOW THESE ACTIONS WILL PREVENT RECURRENCE; C) IF NOT POSSIBLE TO CORRECT THE VIOLATIONS IN 30 DAYS, WITHIN 30 DAYS, SUBMIT A COMPREHENSIVE PLAN TO DO SO IN THE SHORTEST POSSIBLE TIME; AND D) WITHIN 45 DAYS, ARRANGE TO MEET WITH EPA AND SHOW CAUSE.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown