← EPA enforcement cases

EDINGER ENGINEERING - OWENBY WELL NO. 1

Administrative - Formal · FY2000 · — · Final Order With Penalty · 40535

$650
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
06-2000-0920
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

1. SECTION 311(B)(6)(B)(I) OF THE CLEAN WATER ACT ( CWA ), 33 U.S.C. SECTION 1321(B)(6)(B)(I), AS AMENDED BY THE OIL POLLUTION ACT OF 1990. 2. EDINGER ENGINEERING, OWENBY WELL NO. 1 SE/SE/4 SEC. 32, T9 N, R1 E OKLAHOMA CITY, CLEVELAND COUNTY, OKLAHOMA 73139 3. RESPONDENT WAS IN VIOLATION OF SECTION OF 311(J) OF THE CWA BY: 1) NO EVIDENCE OF THREE YEAR REVIEW OF PLAN BY OWNER/OPERATOR; 2) NO PLAN AMENDMENT(S) IF THE FACILITY HAS HAD A CHANGE IN: DESIGN, CONSTRUCTION, OPERATION, OR MAINTENANCE WHICH AFFECTS THE FACILITY'S DISCHARGE PO- TENTIAL; 3) WRITTEN PROCEDURES AND A RECORD OF INSPECT- IONS ARE NOT MAINTAINED FOR THREE YEARS; 4) WALLS OF CON- TAINMENT SYSTEM ARE SLIGHTLY ERODED OR HAVE LOW AREAS; AND 5) INADEQUATE OR NO FLOWLINE MAINTENANCE PROGRAM. 4. RELIEF SOUGHT PURSUANT TO SECTION 311(B)(6)(B)(I) OF THE CWA, EPA ASSESSED THE RESPONDENT A CIVIL PENALTY OF $650 FOR THE VIOLATIONS CITED.

Source

Authoritative
EPA ECHO
Machine