← EPA enforcement cases

AUI GENERAL CONTRACTORS, INC., CENTER OPERATING COMPANY, L.P

Administrative - Formal · FY2001 · — · — · 41731

—
Penalty
—
Cost recovery
$4K
Compliance action

Case

Case Number
06-2001-5186
Type
Administrative - Formal
Lead
EPA
Outcome
—
Multimedia
N
Self-disclosure
N

Defendants (5)

Summary

1. SECTIONS 308(A) AND 309(A) OF THE CLEAN WATER ACT ( CWA ) 33 U.S.C. SECTION 1318(A) AND 1319(A). 2. A. AUI GENERAL CONTRACTORS, INC., A TEXAS CORPORATION B. CENTER OPERATING COMPANY, L.P., A TEXAS PARTNERSHIP C. ED BELL CONSTRUCTION COMPANY, A TEXAS CORPORATION D. HILLWOOD URBAN SERVICES, L.P., A TEXAS PARTNERSHIP E. JOHN BURNS CONSTRUCTION CO. OF TEXAS, A TEXAS CORP. FACILITY: AMERICAN AIRLINES ARENA NORTHEAST SIDE OF THE INTERSECTION OF WOODALL ROGERS FREEWAY AND I-35 DALLAS, DALLAS COUNTY, TEXAS 75201 3. RESPONDENTS WERE IN VIOLATION OF SECTION 301 OF THE CWA BY EACH DAY THAT RESPONDENTS CONDUCTED THE RELEVANT AC- TIVITIES AND OPERATED THE FACILITY WITHOUT NPDES PERMIT COVERAGE. 4. RELIEF SOUGHT PURSUANT TO SECTIONS 308(A) AND 309(A) OF THE CWA, EPA ISSUED AN ADMINISTRATIVE ORDER (AO) THAT ORDERED THE RESPONDENTS TO: A) WITHIN 10 DAYS, OBTAIN NPDES PERMIT COVERAGE, SUBMITTING A COPY OF THE APPLICA- TIONS, CONFIRMATIONS OF COVERAGE, AND PERMIT NUMBERS TO EPA; B) WITHIN 10 DAYS, TAKE CORRECTIVE ACTION TO CORRECT THE DEFICIENCIES AND ELIMINATE AND PREVENT RECURRENCE OF THE VIOLATIONS CITED AND TO COME INTO COMPLIANCE; C) PRO- VIDE THE DATE AT WHICH EARTH DISTURBING ACTIVITIES BEGAN AT THE FACILITY FOR EACH PROJECT;

Source

Authoritative
EPA ECHO
Machine