DEFENDANT IS SUBJECT TO NOTICE, TESTING, AND EMISSION LIMIT REQUIREMENTS OF THE NSPS FOR ASPHALT CONCRETE PLANTS, 40CFR 60(I) SECT. 90-93. DEFENDANT FAILED TO 1) GIVE NOTICE OF ANTICIPATED DATE OF INITIAL START-UP; 2) GIVE NOTICE OF ACTUAL DATE OF START-UP; 3) PERFORM PERFORMANCE TEST AND FINISH EPA WRITTEN TEST REPORT; 4) RESPOND TO EPA SEC. 114 ORDER OF 1/21/85 REQUESTING INFORMATION ON START-UP AND OPERATION. REPRESENTATIVES OF DEFENDANT VERBALLY ADVISED STATE OF IOWA THAT THE FACILITY OPERATED IN 1984, BUT IN RESPONSE TO STATE'S LETTER OF 9/84 RE: FAILURE TO GIVE NOTICE, TEST, ETC., DEFENDANT SAID THERE WAS NOT ENOUGH BUSINESS IN 1984 TO RUN THE PLANT LONG ENOUGH TO DO A TEST (I.E. THAT 6 HRS. CONTINUOUS OPERATION IS NECESSARY). REGION VII ISSUED SEC. 114 ORDER 1/85 REQUESTING INFORMATION ON START-UP DATE W/IN 14 DAYS. DEFENDANT DID NOT RESPOND. IOWA ISSUED ORDER 2/85 REQUESTING NOTICE, TESTING, ETC. BUT NO PENALTIES.