← EPA enforcement cases

STROTHER FIELD INDUSTRIAL PARK SUPERFUND SITE

Judicial · FY2001 · — · Final Order With Specified Cost Recovery · 47230

—
Penalty
$125K
Cost recovery
—
Compliance action

Case

Case Number
07-2001-0077
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
Multimedia
N
Self-disclosure
N

Defendants (7)

Summary

1/31/01: EPA ON 01/30/01 REFERRED A REMEDIAL ACTION CONSENT DECREE TO THE DEPARTMENT OF JUSTICE FOR THE ABOVE SITE. TH E CONSENT DECREE PROVIDES FOR PAYMENT OF A TOTAL OF $460,000 TOWARDS EPA'S COSTS AND PROVIDES FOR THE PAYMENT OF ALL EPA 'S COSTS INCURRED AFTER 4/30/00. WORK TO DATE AT THE SITE H AS BEEN PERFORMED UNDER A UAO FOR RD/RA. THE REMEDY TO BE I MPLEMENTED BY THE DEFENDANTS IS MONITORED NATURAL ATTENUATIO N OF GROUND WATER AND A LIMITED AMOUNT OF SOIL CAPPING OF SO URCE AREAS OF CHLORINATED SOLVENTS CONTAMINATION. IN THE EV ENT NATURAL ATTENUATION IS DETERMINED IN FUTURE TO NOT BE WO RKING, OTHER REMEDIES WILL HAVE TO BE STUDIED AND IMPLEMENTE D BY THE DEFENDANTS. CERCLA 122(H) ADMINISTRATIVE CASHOUT S ETTLEMENTS WITH TWO PARTIES (ENERGY PLUS, INC. AND MONTGOMER Y KONE, INC.) PREVIOUSLY REIMBURSED A TOTAL OF $50,000 OF TH E GOVERNMENT'S COSTS. THE SETTLING DEFENDANTS ARE: GENERAL ELECTRIC COMPANY, GREI F BROS. CORPORATION, , GORDON-PIATT ENERGY GROUP, INC., TENN ECO AUTOMOTIVE, INC., CITY OF WINFIELD, KANSAS, CITY OF ARKANSAS CITY, KANSAS, STR OTHER FIELD COMMISSION. THE DEPARTMENT OF DEFENSE IS CONTRI BUTING $75,000 (TOWARDS THE $460,000 TOTAL) TO CASH OUT FOR ALLEGED LIABILITY IT MAY HAVE WITH RESPECT TO THE SITE FOR R ELEASES OF SOLVENTS DURING THE GOVERNMENT'S OWNERSHIP OF TH E SITE DURING WW II.

Source

Authoritative
EPA ECHO