← EPA enforcement cases

EBASCO CONSTRUCTORS, INC./LOSINGER USA, INC. JOINT VENTURE

Judicial · FY1991 · — · Final Order With Penalty · 52266

$320K
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
09-1991-0039
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
DOJ Docket
90-5-2-1-1677
Multimedia
N
Self-disclosure
N

Defendants (3)

Summary

EBASCO CONSTRUCTORS, INC./LOSINGER U.S.A. INC., JOINT VENTURE ( ELJV ) IS BUILDING THE NEW WADDELL DAM AT LAKE PLEASANT IN NORTHERN MARICOPA COUNTY, ARIZONA. IT IS THE LARGEST EARTHEN DAM CONSTRUCTION PROJECT PRESENTLY ONGOING IN THE UNITED STATES. ELJV IS CONSTRUCTING THE DAM OUTOF PROCESSED (CRUSHED) ROCK. ELJV COLLECTS THE RAW MATERIAL FOR THE DAM FROM LAND CONTROLLED BY THE U.S. BUREAU OF RECLAMATION AND THEN TAKES IT TO A PROCESSING FACILITY WHERE IT IS CRUSHED, SCREENED, SORTED, WASHED, AND BLENDED INTO MATERIAL SUITABLE FOR DAM CONSTRUCTION. THIS PROCESSED MATERIAL IS THEN TRUCKED FROM THE PROCESSING FACILITY AND ADDED TO THE DAM ITSELF. IN VIOLATION OF NEW SOURCE PERFORMANCE STANDARDS ( NSPS ), ELJV FAILED TO NOTIFY EPA OF THE CONSTRUCTION AND STARTUP OF CERTAIN PORTIONS OF THE PROCESSING FACILITY AND ALSO FAILED TO PERFORM CERTAIN EMISSIONS TESTS. FUTHERMORE, BECAUSE THIS PROJECT IS LOCATED IN A NONATTAINMENT AREA FOR TSP/PM10 AND BECAUSE THE PROCESSING FACILITY IS A MAJOR SOURCE OF THESE POLLUTANTS, CONSTRUCTION OF THE PROCESSING PLANT ALSO TRIGGERED APPLICATION OF MARICOPA COUNTY'S NEW SOURCE REVIEW ( NSR ) PERMITTING PROGRAM. ELJV VIOLATED MARICOPA COUNTY'S NSR RULES, WHICH HAVE BEEN INCORPORATED INTO ARIZONA'S STATE IMPLEMENTATION PLAN ( SIP ) BY FAILING TO OBTAIN A PERMIT BEFORE IT BEGAN CONSTRUCTING THE PLANT. EPA HAS ISSUED A NOTICE OF VIOLATION (

Source

Authoritative
EPA ECHO
Machine