COOLEY INC

Administrative - Formal · FY2007 · — · Final Order With Penalty · 600029383

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
01-2007-1213
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

Cooley conducted performance tests on a add-on control device (a thermal oxidizer) on November 7 and 20, 2006. Based on the test results and additional investigation regarding its thermal oxidizer, Cooley determined that the oxidizer could not be repaired or modified in a manner that would allow Coater #5 to achieve the required emissions standard under 40 CFR Part 63, Subpart OOOO (Fabric Coating NESHAP) without installing a new oxidizer. Cooley was required to meet the emission standard for the Fabric Coating NESHAP by May 29, 2006. Cooley notified EPA in January 2007 of Coater #5's inability to comply with the Fabric Coating NESHAP. Cooley also discussed its plans to order, construct and install a new regenerative thermal oxidizer (RTO) at its facility as soon as possible. In February 2007, EPA issued an administrative order to Cooley that set forth a schedule for the construction, installation and tesing of the new RTO. Cooley completed the construction, installation and testing of the new RTO by the end of August 2007.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown