Case Number
01-2007-2028
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

AS THE RESULT OF AN INSPECTION IN FEBRUARY 2007 OF A HOME CONSTRUCTION SITE IN HOLDEN, MA, EPA FOUND THAT RESPONDENT DID NOT HAVE STORM WATER PERMIT COVERAGE FOR THE SITE. EPA ALSO FOUND THAT THE STORM WATER POLLUTION PREVENTION PLAN FOR THE SITE LACKED SEVERAL ELEMENTS REQUIRED BY EPA's GENERARL STORM WATER PERMIT, AND THAT RESPONDENT ALSO FAILED TO CONDUCT ROUTINE STORM WATER INSPECTIONS FOR THE SITE.