← EPA enforcement cases

Reliance Supply Company, Inc. (Complaint/CAFO)

Administrative - Formal · FY2003 · — · Final Order With Penalty · 96157

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
04-2003-1507
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
—
Self-disclosure
N

Defendants (1)

Summary

5/13/03 - CAFO ISSUED (NO COMPLAINT FILED). $1,000 DUE WITHIN 30 DAYS. EPA ASSERTS THAT SECTION 183(e) OF THE CAA AND THE REGULATIONS PROMULGATED AT 40 CFR PART 59, SUBPART D ESTABLISH THAT EACH MANUFACTURER OR IMPORTER OF ANY ARCHITECTURAL COATING SUBJECT TO THE PROVISIONS OF THIS SUBPART SHALL SUBMIT AN INITIAL NOTIFICATION REPORT NO LATER THAN SEPTEMBER 13, 1999, OR WITHIN 180 DAYS AFTER THE DATE THAT THE FIRST ARCHITECTURAL COATING IS MANUFACTURED OR IMPORTED, WHICHEVER IS LATER. EPA ASSERTS THAT RESPONDENT DID SUPPLY THIS DATA ON JANUARY 12, 2003, TO EPA AND WAS IN BUSINESS TO MANUFACTURE OR IMPORT AN ARCHITECTURAL COATING AT LEAST AS EARLY AS SEPTEMBER 13, 199

Source

Authoritative
EPA ECHO