← EPA enforcement cases

Noel, Raymond and Reve Development Corp. (Consent Agmt)

Administrative - Formal · FY2003 · — · Final Order No Penalty · 99283

—
Penalty
—
Cost recovery
—
Compliance action

Case

Case Number
04-2003-5763
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
—
Self-disclosure
N

Defendants (2)

Summary

6/20/03 - CONSENT AGMT ISSUED. ORDER REQUIRES RESPONDENT TO: 1. SUBMIT AN AFTER-THE-FACT PERMIT APPLICATION TO THE U.S. ARMY CORPS OF ENGINEERS FOR ALL PREVIOUS WORK CONDUCTED IN WETLANDS AND WATERS OF THE U.S. AND ALSO FOR FUTURE WORK NEEDED TO CMOPLETE THE PROJECT ONSITE. RESPONDENTS SHALL PROVIDE EPA WITH A COPY OF THE PERMIT APPLICATION. 2. WITHIN 30 DAYS OF THE EFFECTIVE DATE OF THIS AGMT, RESPONDENTS AGREE TO DONATE $10,000 TO GARCON PENINSULA MITIGATION BANK. PAYMENT WILL BE USED TO RESTORE AND/OR CREATE WETLANDS AND/OR SEAGRASS HABITATS IN THE SANTA ROSA AND ESCAMBIA COUNTIES AND SURROUNDING AREAS TO PARTIALLY COMPENSATE FOR THE ENVIRONMENTAL DAMAGE THAT OCCURRED AT THE THREE DISCHARGE AREAS

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown