← EPA Federal Register rules

Air Plan Approval; Ohio; Regional Haze Glatfelter BART SIP Revision

air-emissions · Rule · Published 2016-03-04 · Effective 2016-04-04 · OH · 81 FR 11445

Document

Document number
2016-04730
Federal Register citation
81 FR 11445
CFR reference
40 CFR 52
Type
Rule
Action
Final rule.
Category
air-emissions
Publication date
2016-03-04
Effective date
2016-04-04
State
OH
EPA docket
EPA-R05-OAR-2014-0362

Abstract

The Environmental Protection Agency (EPA) is taking final action to extend the compliance date for the Best Available Retrofit Technology (BART) emission limits for sulfur dioxide (SO<INF>2</INF>) at the P.H. Glatfelter Company (Glatfelter) facility submitted as part of its State Implementation Plan (SIP) Revision on April 14, 2014. Specifically, EPA is extending the compliance date for the SO<INF>2</INF> emission limits applicable to Boilers No. 7 and No. 8 at Glatfelter by 25 months, from December 31, 2014, to January 31, 2017. We have reviewed this SIP revision and concluded that it meets the requirements of the Clean Air Act and the regional haze rule and because BART requirements continue to be met.

Source

Authoritative
Federal Register document
Machine
JSON-LD · Markdown